Even more efficiency in logistics — this is now on the agenda of the food discounter in Switzerland Denner. The central warehouse in Mägenwil AG has been modernized in recent months with modern automation technology from Swisslog. The warehouse is the elementary hub for supplying over 250 Denner stores with groceries and important household products. Despite Corona restrictions and a tight schedule, all the work went according to plan.
It was an ambitious project: The modernization of the AG distribution center in Mägenwil, Canton Aargau. Now it has been successfully completed. Swisslog AG from Buchs AG has equipped a high-bay food warehouse for hard goods with modern automation — in pandemic times, during ongoing operations with constantly high capacity utilization.
“As a discounter, we are all about efficiency, while at the same time the demands on logistics are constantly increasing. Ensuring the availability of goods as well as fast and error-free delivery to over 250 stores are decisive factors for the project, while at the same time the conversion also offers added ecological value,” explains Daniel Kindler, Head of the Mägenwil distribution center. “Since the new installation has been in operation, material flows are more efficient and conserve resources,” says Kindler.
Seamlessly coordinated processes
Swisslog replaced twelve older pallet stacker cranes with modern ones and installed new pallet conveyor technology. In addition, two new mezzanine levels were built. In the process, the available time window of only five months was very narrow.
“The challenges were great. The Corona protection measures demanded a lot from us and yet we managed to complete all the work within the specifications.”
- Mario Flory, Project Manager
Part of securing the food supply
In order to disrupt operations at Denner as little as possible, Swisslog undertook the modernization not only during shift times, but also at night and on weekends. In addition, the team worked in stages for major installation measures.
Flory explains, “To enable the removal of the stacker cranes, about a quarter of the high-bay warehouse was emptied by placing a partial assortment externally and picking it there. Thus, we were able to remove 3 old stacker cranes at once and install 3 new ones in 10 days.” After their installation and software connection, goods in the high-bay warehouse were relocated so that the next shelf area became free. Swisslog saved time for the ramp-up in real operation through extensive tests in advance, on Saturdays and Sundays.
Flory concludes: “We are pleased that we were able to play our part in securing the food supply at Denner.